Situation:

previous contractor left the customer in a lurch and a short deadline.


Mission:

-processing plant

-build mezzanine were other contractor left off

-multiple days

-Fulton industrial

-E rate


Execution:

-build stringers

-assemble frame and install deck and handrails 


Administration:

communicate plan

draw pay on regular schedule 


Command:

Tech: Clint

Mgt: xxx xxxxx

 
 
 
 
 

Situation:

-Customer requested repair on gate.


Mission:

-Prep, Weld

-Steel

-Senoia Georgia

-Residential address

-Tuesday Morning 

-NH Scheduled Appointment 


Execution:

-Assessment 

-Fitment 

-Gouged 

-Weld


Administration:

-Collect final payment.